Our Projects

Project Skelmersdale

  • DNO: Electricity North West, 33kV
  • Installed Capacity: 20.28 MW
  • Engine OEM: MWM
  • Status: Under Construction
SCOD: Jan 2020

Project St. Helens

  • DNO: Electricity North West, 33kV
  • Installed Capacity: 14 MW
  • Engine OEM: MWM
  • Status: Under Construction
SCOD: Feb 2020

Project Eyre Street

  • DNO: WPD WMID
  • Installed Capacity: 7 MW
  • Engine OEM: TBD
  • Status: Construction starting by April 2020

Project Rectory Farm

  • DNO: WPD WMID
  • Installed Capacity: 7.6 MW
  • Engine OEM: TBD
  • Status: Construction starting by April 2020

Project Enderby

  • DNO: WPD WMID
  • Installed Capacity: 6 MW
  • Engine OEM: TBD
  • Status: Construction starting by April 2020

Project Sough Road

  • DNO: ENWL
  • Installed Capacity: 7 MW
  • Engine OEM: TBD
  • Status: Construction starting by April 2020

Project Rochdale

  • DNO: ENWL
  • Installed Capacity: 7.6 MW
  • Engine OEM: TBD
  • Status: Construction starting by April 2020

Project Wheatly

  • DNO: SEPD
  • Installed Capacity: 7 MW
  • Engine OEM: TBD
  • Status: Construction starting by April 2020

Project Pinxton

  • DNO: WPD WMID
  • Installed Capacity: 7.3 MW
  • Engine OEM: TBD
  • Status: Construction starting by April 2020